How to Evaluate a Construction Time Impact Analysis

A time impact analysis should identify a dated event, a defensible contemporaneous schedule update, the inserted logic, the forecast effect and supporting contemporaneous evidence.

Direct answer

A time impact analysis should identify a dated event, a defensible contemporaneous schedule update, the inserted logic, the forecast effect and supporting contemporaneous evidence.

What is the analysis based on?

Identify the contract requirements and schedule methodology first. Then establish the exact schedule data date, affected path and fragnet logic, verifying that the cited event and sequence are supported by records.

What common red flags deserve attention?

  • Using a schedule update remote from the event without justification
  • Missing or unsupported fragnet logic
  • Assuming delay to a milestone without establishing affected path
  • Ignoring other concurrent work or project changes
  • Mixing forecast and observed impacts without explaining methodology

What is the limitation of a preliminary review?

A preliminary technical screen identifies issues for further assessment; it is not a legal entitlement opinion or comprehensive forensic finding. Selection of methodology depends on the contract, available records and expert scope.

Related guidance

Discuss a specific project question

Tell PPC Group what decision you need to make. Please do not send privileged or confidential records through the initial inquiry.

Request a project consultation ↗

Reviewed November 26, 2026. General information only; findings and deliverables depend on project documents and an agreed scope.