Is the Contractor’s Recovery Schedule Credible?

A credible recovery schedule documents exactly how time will be regained, which resources and approvals it requires, and what risks remain if the plan does not perform.

Direct answer

A credible recovery schedule documents exactly how time will be regained, which resources and approvals it requires, and what risks remain if the plan does not perform.

What should the contractor demonstrate?

  • Specific recovery actions rather than only shorter activity durations
  • Manpower and productivity assumptions supported by actual capacity
  • Trade access, temporary works, logistics and safety coordination
  • Released materials, approved submittals and realistic deliveries
  • Authority having jurisdiction inspection and commissioning windows
  • Measureable weekly milestones for tracking results

What does a useful Owner decision memo include?

Compare baseline and recovery milestones; identify assumptions that remain unverified; outline options and associated costs; and recommend monitoring thresholds that would trigger another decision.

Related guidance

Discuss a specific project question

Tell PPC Group what decision you need to make. Please do not send privileged or confidential records through the initial inquiry.

Request a project consultation ↗

Reviewed November 26, 2026. General information only; findings and deliverables depend on project documents and an agreed scope.